Schwechat

Revitalisation of the Schwechat in Traiskirchen gets underway

On 3 February 2020, the moment finally arrived: construction work began to revitalise approximately 500 metres of the Schwechat in the Kaiserau, below the bridge to the Stadtrandsiedlung in the cadastral community of Möllersdorf, municipality of Traiskirchen.

The background: in January 2019, the Schwechat Water Association applied for the permits required under water, nature conservation and forestry law for the project “Revitalisation of the Schwechat in Traiskirchen”. Following approval by the Baden district authority in summer 2019, the project was implemented in winter 2020.

The Schwechat is being freed from its straight alignment and stone embankments to allow the river to resume its characteristic lateral movement. Three groynes built in the riverbed are intended to initiate this process.